Thursday, December 28, 2023
27 DEC 2023 HKL
NSC GROUP
[09:56, 27/12/2023] Azman HKL: Siye progress photo.
27/12/2023.
10th floor. TA1. Slab rebar & M&E in progress. 9th floor. TA2. Slab formwork and scaffolding in progress.
[09:56, 27/12/2023] Azman HKL: 4th floor. Z7. Slab rebar in progress. 6th floor. Z6. Slab formwork in progress
[09:56, 27/12/2023] Azman HKL: 6th floor. TB5. Slab formwork in progress.
18 DEC 2023 HKL
NSC GROUP
[09:31, 18/12/2023] Azman HKL: Site progress photo.
18/12/2023.
9th floor. TA1. Slab cast. Column rebar and formwork in progress.
[09:31, 18/12/2023] Azman HKL: 7th floor. Zone 4. Slab formwork in progress.
[09:31, 18/12/2023] Azman HKL: 9th floor. TA2. Slab formwork in progress.
[09:31, 18/12/2023] Azman HKL: Basement. Z5C. Fire water tank plinth and pump plinth in progress.
[09:31, 18/12/2023] Azman HKL: 6th floor. Z6. Beam formwork in progress.
[09:31, 18/12/2023] Azman HKL: Basement. Z9. Lift pit wall rebar in progress.
[09:52, 18/12/2023] Azman HKL: Morning @~ShawnChia. Your genset supplier informed me that today your lorry crane chief will come to inspect the site's. Please confirm and set the time to join the inspection. TQ. π
[11:12, 18/12/2023] Azman HKL: Rd floor. Ramp4. Slab formwork and column rebar in progress.
[11:12, 18/12/2023] Azman HKL: 6th floor. TB3. Slab formwork in progress
[12:14, 18/12/2023] Azman HKL: Today, join inspection with Genset supplier, Chief of lorry crane, DCC, Site safety and HKL onsite, 3.00pm. @~π
πΆπ ππ½πππ @~ShawnChia @Jimmy HKL @~Leppong
12 DEC 2023 HKL
NSC GROUP
[09:19, 12/12/2023] Azman HKL: Good morning.
Site progress photo.
12/12/23.
8th floor. TA1/a. Slab cast. Congratulations everyone, we managed to complete the work as planned yesterday. Everyone has been working hard especially King Hong till completion. ππ»ππ»ππ» Next floor, should be no problem. πͺπͺπͺ. Keep pushing and encouraging.
[09:23, 12/12/2023] Azman HKL: 9th floor. TA1. Slab formwork and support in progress
[09:23, 12/12/2023] Azman HKL: Basement. Z9. Lift pit wall rebar, retaining wall rebar in progress.
[09:23, 12/12/2023] Azman HKL: 6th floor. TB5. Slab formwork in progress.
[09:25, 12/12/2023] +60 14-379 2990: @60128433889 Kami request buka formwork cold water tank, basement.. kami jalan smoke spill duct. Tq.
[09:25, 12/12/2023] Azman HKL: Basement. Z8. Support rebar in progress.
[09:36, 12/12/2023] Raymond Chong. Y. F (HKL P. Manager): 5C
[09:38, 12/12/2023] Azman HKL: Okay. Noted.
[10:19, 12/12/2023] Azman HKL: For info. As informed by the DCC supplier, a container will arrive tomorrow 13/12/23 at 4-5pm and parked at the designated location. The next day equipment will be taken out and stored at the ground floor using a Lorry crane. @~Leppong tolong assist. @Jimmy HKL nanti minta tolong kita atur bsok maw barricade itu kawasan. Sama buka sikit itu pagar sementara.
[10:20, 12/12/2023] Jimmy HKL: ok
[10:22, 12/12/2023] Azman HKL: 3rd floor. Water tank room. @~Roxas Ng (Kai) tolong kejar subcon plastering ini bilik juga. ππ
[10:27, 12/12/2023] Azman HKL: Sda inform subcon. Nanti tolong followup di site.π
[10:28, 12/12/2023] +60 16-832 2597: Sedang saya kejar ya ππ»
[14:32, 12/12/2023] Azman HKL: M&E Coordination meeting today 3.30pm after the subcon weekly meeting at the meeting room.
[14:34, 12/12/2023] +60 16-837 8881: Noted
[15:26, 12/12/2023] Azman HKL: New Casting Plan
BF - 9B RC wall - 14/12/23
BF - 9C -15/12/23
BF - 5C/a - 15/12/23
9F - TA/1 - 15/12/23
6F - TB5 - 16/12/23
6F - Z6 - 19/12/23
9F - TA/2 -21/12/23
6F - TB3 - 21/12/23
4F - Z7 - 21/12/23
6F - Z4 - 26/12/23
Please coordinate material, man power and drawing onsite. Date may be changed due to site condition.
[15:28, 12/12/2023] Azman HKL: @~Leppong @~Walker Yapi @HIDAYA KH office Num please take note
Wednesday, December 27, 2023
28 DEC 2023 HKL
NSC GROUP
[09:14, 28/12/2023] Azman HKL: 4th floor. Z7. Slab rebar and M&E in progress.
[09:33, 28/12/2023] Azman HKL: 10th floor. TA1. Slab cast. TA2. Slab formwork in progress.
[09:33, 28/12/2023] Azman HKL: 6th floor. TB5. Slab formwork in progress.
[09:38, 28/12/2023] Azman HKL: 6th floor. Z6. Slab formwork and rebar in progress.
[09:56, 28/12/2023] Azman HKL: 10th floor. TA2. Done surveyor marking. @HIDAYA KH office Num @~Walker Yapi . π
[10:16, 28/12/2023] HIDAYA KH office Num: okay will start installation after formwork and site clearing done
[13:30, 28/12/2023] Azman HKL: 10 floor. TA2. Formwork in progress.
[13:30, 28/12/2023] Azman HKL: 4th floor. Z7. Slab formwork and rebar in progress. 6fh floor. Z6.Slab rebar in progress.
[13:30, 28/12/2023] Azman HKL: 6th floor. TB5. Slab rebar in progress.
[14:43, 28/12/2023] HIDAYA KH office Num: kami mau request clearing petang ni boleh ka, before jam 3 begitu. takut esok pagi masuk besi suda.
[15:00, 28/12/2023] Azman HKL: Jam 3pm tdk dapat. Mereka masih sedang buat. Dlm jam 5pm baru clear tu.
[15:01, 28/12/2023] Azman HKL: Bos @~π
πΆπ ππ½πππ @~nas4rie tolong ya. πππ