Thursday, December 28, 2023

29 DEC 2023




















 

27 DEC 2023 HKL

 NSC GROUP


[09:56, 27/12/2023] Azman HKL: Siye progress photo.
27/12/2023.
10th floor. TA1. Slab rebar & M&E in progress. 9th floor. TA2. Slab formwork and scaffolding in progress.

[09:56, 27/12/2023] Azman HKL: 4th floor. Z7. Slab rebar in progress. 6th floor. Z6. Slab formwork in progress

[09:56, 27/12/2023] Azman HKL: 6th floor. TB5. Slab formwork in progress.

[15:20, 27/12/2023] Azman HKL: 10th floor. TA1. Pre inspection in progress. M&E services installation are still ongoing.

[16:16, 27/12/2023] +60 14-379 2990: M&E Inspection in progress
.

18 DEC 2023 HKL

 NSC GROUP

[09:31, 18/12/2023] Azman HKL: Site progress photo.
18/12/2023.
9th floor. TA1. Slab cast. Column rebar and formwork in progress.

[09:31, 18/12/2023] Azman HKL: 7th floor. Zone 4. Slab formwork in progress.

[09:31, 18/12/2023] Azman HKL: 9th floor. TA2. Slab formwork in progress.

[09:31, 18/12/2023] Azman HKL: Basement. Z5C. Fire water tank plinth and pump plinth in progress.

[09:31, 18/12/2023] Azman HKL: 6th floor. Z6. Beam formwork in progress.

[09:31, 18/12/2023] Azman HKL: Basement. Z9. Lift pit wall rebar in progress.
[09:52, 18/12/2023] Azman HKL: Morning @~ShawnChia. Your genset supplier informed me that today your lorry crane chief will come to inspect the site's. Please confirm and set the time to join the inspection. TQ. πŸ™

[11:12, 18/12/2023] Azman HKL: Rd floor. Ramp4. Slab formwork and column rebar in progress.

\
[11:12, 18/12/2023] Azman HKL: 6th floor. TB3. Slab formwork in progress
[12:14, 18/12/2023] Azman HKL: Today, join inspection with Genset supplier, Chief of lorry crane, DCC, Site safety and HKL onsite, 3.00pm. @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” @~ShawnChia @Jimmy HKL @~Leppong

[15:52, 18/12/2023] Azman HKL: Site inspection with DCC, Genset Supplier, mobile crane operator and Safety HKL.

12 DEC 2023 HKL

NSC GROUP



[09:19, 12/12/2023] Azman HKL: Good morning. 
Site progress photo. 
12/12/23.
8th floor. TA1/a. Slab cast. Congratulations everyone, we managed to complete the work as planned yesterday. Everyone has been working hard especially King Hong till completion. πŸ‘πŸ»πŸ‘πŸ»πŸ‘πŸ» Next floor, should be no problem. πŸ’ͺπŸ’ͺπŸ’ͺ. Keep pushing and encouraging.

[09:23, 12/12/2023] Azman HKL: 9th floor. TA1. Slab formwork and support in progress

[09:23, 12/12/2023] Azman HKL: Basement. Z9. Lift pit wall rebar, retaining wall rebar in progress.

[09:23, 12/12/2023] Azman HKL: 6th floor. TB5. Slab formwork in progress.

[09:25, 12/12/2023] +60 14-379 2990: @60128433889  Kami request buka formwork cold water tank, basement.. kami jalan smoke spill duct. Tq.

[09:25, 12/12/2023] Azman HKL: Basement. Z8. Support rebar in progress.
[09:36, 12/12/2023] Raymond Chong. Y. F (HKL P. Manager): 5C
[09:38, 12/12/2023] Azman HKL: Okay. Noted. 

[10:19, 12/12/2023] Azman HKL: For info. As informed by the DCC supplier, a container will arrive tomorrow 13/12/23 at 4-5pm and parked at the designated location. The next day equipment will be taken out and stored at the ground floor using a Lorry crane. @~Leppong tolong assist. @Jimmy HKL nanti minta tolong kita atur bsok maw barricade itu kawasan. Sama buka sikit itu pagar sementara.
[10:20, 12/12/2023] Jimmy HKL: ok

[10:22, 12/12/2023] Azman HKL: 3rd floor. Water tank room. @~Roxas Ng (Kai) tolong kejar subcon plastering ini bilik juga. πŸ™πŸ™
[10:27, 12/12/2023] Azman HKL: Sda inform subcon. Nanti tolong followup di site.πŸ™
[10:28, 12/12/2023] +60 16-832 2597: Sedang saya kejar ya πŸ™πŸ»

[14:32, 12/12/2023] Azman HKL: M&E Coordination meeting today 3.30pm after the subcon weekly meeting at the meeting room.
[14:34, 12/12/2023] +60 16-837 8881: Noted

[15:26, 12/12/2023] Azman HKL: New Casting Plan
BF - 9B RC wall - 14/12/23
BF - 9C -15/12/23
BF - 5C/a - 15/12/23
9F - TA/1 - 15/12/23
6F - TB5 - 16/12/23
6F - Z6 - 19/12/23
9F - TA/2 -21/12/23
6F - TB3 - 21/12/23
4F - Z7 - 21/12/23
6F - Z4 - 26/12/23
Please coordinate material, man power and drawing onsite. Date may be changed due to site condition.
[15:28, 12/12/2023] Azman HKL: @~Leppong @~Walker Yapi @HIDAYA KH office Num please take note

Wednesday, December 27, 2023

28 DEC 2023 HKL

NSC GROUP 
 

[09:14, 28/12/2023] Azman HKL: 4th floor. Z7. Slab rebar and M&E in progress.

[09:33, 28/12/2023] Azman HKL: 10th floor. TA1. Slab cast. TA2. Slab formwork in progress.

[09:33, 28/12/2023] Azman HKL: 6th floor. TB5. Slab formwork in progress.

[09:38, 28/12/2023] Azman HKL: 6th floor. Z6. Slab formwork and rebar in progress.

[09:56, 28/12/2023] Azman HKL: 10th floor. TA2. Done surveyor marking. @HIDAYA KH office Num @~Walker Yapi . πŸ‘†
[10:16, 28/12/2023] HIDAYA KH office Num: okay will start installation after formwork and site clearing done

[13:30, 28/12/2023] Azman HKL: 10 floor. TA2. Formwork in progress.

[13:30, 28/12/2023] Azman HKL: 4th floor. Z7. Slab formwork and rebar in progress. 6fh floor. Z6.Slab rebar in progress.

[13:30, 28/12/2023] Azman HKL: 6th floor. TB5. Slab rebar in progress.
[14:43, 28/12/2023] HIDAYA KH office Num: kami mau request clearing petang ni boleh ka, before jam 3 begitu. takut esok pagi masuk besi suda.
[15:00, 28/12/2023] Azman HKL: Jam 3pm tdk dapat. Mereka masih sedang buat. Dlm jam 5pm baru clear tu.
[15:01, 28/12/2023] Azman HKL: Bos @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” @~nas4rie tolong ya. πŸ™πŸ™πŸ™

28 DEC 2023






















 