[09:31, 18/12/2023] Azman HKL: Site progress photo.
18/12/2023.
9th floor. TA1. Slab cast. Column rebar and formwork in progress.
[09:31, 18/12/2023] Azman HKL: 7th floor. Zone 4. Slab formwork in progress.
[09:31, 18/12/2023] Azman HKL: 9th floor. TA2. Slab formwork in progress.
[09:31, 18/12/2023] Azman HKL: Basement. Z5C. Fire water tank plinth and pump plinth in progress.
[09:31, 18/12/2023] Azman HKL: 6th floor. Z6. Beam formwork in progress.
[09:31, 18/12/2023] Azman HKL: Basement. Z9. Lift pit wall rebar in progress.
[09:52, 18/12/2023] Azman HKL: Morning @~ShawnChia. Your genset supplier informed me that today your lorry crane chief will come to inspect the site's. Please confirm and set the time to join the inspection. TQ. π
[11:12, 18/12/2023] Azman HKL: Rd floor. Ramp4. Slab formwork and column rebar in progress.
[11:12, 18/12/2023] Azman HKL: 6th floor. TB3. Slab formwork in progress
[12:14, 18/12/2023] Azman HKL: Today, join inspection with Genset supplier, Chief of lorry crane, DCC, Site safety and HKL onsite, 3.00pm. @~π
πΆπ ππ½πππ @~ShawnChia @Jimmy HKL @~Leppong