28 DEC 2023 HKL

NSC GROUP 
 

[09:14, 28/12/2023] Azman HKL: 4th floor. Z7. Slab rebar and M&E in progress.

[09:33, 28/12/2023] Azman HKL: 10th floor. TA1. Slab cast. TA2. Slab formwork in progress.

[09:33, 28/12/2023] Azman HKL: 6th floor. TB5. Slab formwork in progress.

[09:38, 28/12/2023] Azman HKL: 6th floor. Z6. Slab formwork and rebar in progress.

[09:56, 28/12/2023] Azman HKL: 10th floor. TA2. Done surveyor marking. @HIDAYA KH office Num @~Walker Yapi . πŸ‘†
[10:16, 28/12/2023] HIDAYA KH office Num: okay will start installation after formwork and site clearing done

[13:30, 28/12/2023] Azman HKL: 10 floor. TA2. Formwork in progress.

[13:30, 28/12/2023] Azman HKL: 4th floor. Z7. Slab formwork and rebar in progress. 6fh floor. Z6.Slab rebar in progress.

[13:30, 28/12/2023] Azman HKL: 6th floor. TB5. Slab rebar in progress.
[14:43, 28/12/2023] HIDAYA KH office Num: kami mau request clearing petang ni boleh ka, before jam 3 begitu. takut esok pagi masuk besi suda.
[15:00, 28/12/2023] Azman HKL: Jam 3pm tdk dapat. Mereka masih sedang buat. Dlm jam 5pm baru clear tu.
[15:01, 28/12/2023] Azman HKL: Bos @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” @~nas4rie tolong ya. πŸ™πŸ™πŸ™