[09:19, 12/12/2023] Azman HKL: Good morning. 
Site progress photo. 
12/12/23.
8th floor. TA1/a. Slab cast. Congratulations everyone, we managed to complete the work as planned yesterday. Everyone has been working hard especially King Hong till completion. 👍🏻👍🏻👍🏻 Next floor, should be no problem. 💪💪💪. Keep pushing and encouraging.

[09:23, 12/12/2023] Azman HKL: 9th floor. TA1. Slab formwork and support in progress

[09:23, 12/12/2023] Azman HKL: Basement. Z9. Lift pit wall rebar, retaining wall rebar in progress.

[09:23, 12/12/2023] Azman HKL: 6th floor. TB5. Slab formwork in progress.

[09:25, 12/12/2023] +60 14-379 2990: @60128433889  Kami request buka formwork cold water tank, basement.. kami jalan smoke spill duct. Tq.

[09:25, 12/12/2023] Azman HKL: Basement. Z8. Support rebar in progress.
[09:36, 12/12/2023] Raymond Chong. Y. F (HKL P. Manager): 5C
[09:38, 12/12/2023] Azman HKL: Okay. Noted. 

[10:19, 12/12/2023] Azman HKL: For info. As informed by the DCC supplier, a container will arrive tomorrow 13/12/23 at 4-5pm and parked at the designated location. The next day equipment will be taken out and stored at the ground floor using a Lorry crane. @~Leppong tolong assist. @Jimmy HKL nanti minta tolong kita atur bsok maw barricade itu kawasan. Sama buka sikit itu pagar sementara.
[10:20, 12/12/2023] Jimmy HKL: ok

[10:22, 12/12/2023] Azman HKL: 3rd floor. Water tank room. @~Roxas Ng (Kai) tolong kejar subcon plastering ini bilik juga. 🙏🙏
[10:27, 12/12/2023] Azman HKL: Sda inform subcon. Nanti tolong followup di site.🙏
[10:28, 12/12/2023] +60 16-832 2597: Sedang saya kejar ya 🙏🏻

[14:32, 12/12/2023] Azman HKL: M&E Coordination meeting today 3.30pm after the subcon weekly meeting at the meeting room.
[14:34, 12/12/2023] +60 16-837 8881: Noted

[15:26, 12/12/2023] Azman HKL: New Casting Plan
BF - 9B RC wall - 14/12/23
BF - 9C -15/12/23
BF - 5C/a - 15/12/23
9F - TA/1 - 15/12/23
6F - TB5 - 16/12/23
6F - Z6 - 19/12/23
9F - TA/2 -21/12/23
6F - TB3 - 21/12/23
4F - Z7 - 21/12/23
6F - Z4 - 26/12/23
Please coordinate material, man power and drawing onsite. Date may be changed due to site condition.
[15:28, 12/12/2023] Azman HKL: @~Leppong @~Walker Yapi @HIDAYA KH office Num please take note