Wednesday, June 19, 2024

19 JUN 2024 HKL

SITE EG MALL



[09:45, 19/06/2024] +60 16-880 4632: L14
[09:45, 19/06/2024] Azman HKL: Request for joint inspection. 11th floor. Hotel unit. Conduit Electrical and ELV at hotel room brickwall at 10am. @~sam @Kadapi J. PROMES
[10:58, 19/06/2024] Kadapi J. PROMES: Saya cuti ni hari.
[11:22, 19/06/2024] Azman HKL: Noted.πŸ‘Œ



[16:45, 19/06/2024] Azman HKL: Thanks for inform @HIDAYA KH office Num tolong cek sekali ya itu pipe πŸ™.


NSC GROUP
 
[09:12, 19/06/2024] Azman HKL: Good morning.
Site progress photo.
19/6/24.
21st floor. Tower A.

[09:13, 19/06/2024] Azman HKL: 7th floor. TB6. Slab riser. Slab formwork and rebar in progress

[09:14, 19/06/2024] Azman HKL: 7th floor. TB4&TB5. Column rebar in progress

[09:15, 19/06/2024] Azman HKL: 3rd floor. Z8.


[09:22, 19/06/2024] +60 14-379 2990: Morning . @Azman HKL @~nas4rie minta tolong buka formwork riser.. ducting ready sudah

[09:41, 19/06/2024] Azman HKL: @~nas4rie minta tolong. πŸ™
[09:47, 19/06/2024] +60 12-559 6863: Gd morning @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” Can we do a pre inspection for sesb sub station tommorrow 12:30pm? Get elec nsc to join. I will also get turnkey contractor to join. FYI, turnkey has been approved. We have 6 months to energize the sub station. Preceeded by Lunch at 1pm at our usual πŸ˜ƒ
[09:47, 19/06/2024] +60 12-559 6863: @~Lawrence Yapp please send your representative ya

[12:34, 19/06/2024] +60 14-379 2990: @Azman HKL ..man, corridor level 8 kerja plastering bila boleh siap ni? Kami mau pasang balik ducting..kami takut ducting tambah damage..
[13:16, 19/06/2024] Azman HKL: @EG Mall Shafee tolong atur sama subcon GnB bro. πŸ™
[13:20, 19/06/2024] EG Mall Shafee: Ok
[13:45, 19/06/2024] Azman HKL: Tolong update ini progress work untuk meeting bsok. @~ShawnChia @Recky Econmech @HIDAYA KH office Num @~At Work
[14:05, 19/06/2024] +60 10-822 2014: Maklum
[14:07, 19/06/2024] +60 17-866 0355: Ok bo

Monday, June 17, 2024

18 JUN 2024










 

18 JUN 2024 HKL

SITE EG MALL


NSC GROUP 

[08:43, 18/06/2024] Azman HKL: Site progress photo.
18/6/24.
21st floor. Tower A.

[08:44, 18/06/2024] Azman HKL: 7th floor. Slab rebar in progress.

[08:45, 18/06/2024] Azman HKL: 7th floor. Column rebar in progress.
[08:51, 18/06/2024] Azman HKL: Good morning all, today site coordination meeting at 2pm, please inform all respective subcons to attend including tilers, painters, aluminium NSC and all M&E. @~ShawnChia @EG MALL ECONMECH Dart @HIDAYA KH office Num @~YoonYK @~At Work

[09:36, 18/06/2024] Azman HKL: 12th floor. Hotel FFL marking at lift wall in progress. 14th to 8th floor. @~YoonYK πŸ‘†


[09:38, 18/06/2024] Azman HKL: 12th floor. ELV conduit installation at brickwall in progress.
[09:40, 18/06/2024] +60 19-821 8251: Noted thank you.

[09:46, 18/06/2024] Azman HKL: Marking di pintu ya. Macam ini.

[09:50, 18/06/2024] Azman HKL: 9th floor. Installation plumbing pipe at brickwall in progress.

[10:07, 18/06/2024] +60 18-960 2589: pungut sampah L12

[10:10, 18/06/2024] Azman HKL: 13th floor. Ceiling height inspection for ACMV services.


[11:28, 18/06/2024] Azman HKL: 14th floor

[14:33, 18/06/2024] Azman HKL: Site coordination meeting. 2pm

Saturday, June 15, 2024

15 JUN 2024 HKL

SITE EG MALL 

[10:34, 15/06/2024] +60 16-832 2597: Unscheduled site inspection for 4F electrical room for brick setting out
[10:35, 15/06/2024] +60 16-832 2597: @~Johnny we will have another inspection by 2:30pm today later for 5th floor
[10:40, 15/06/2024] +60 16-880 4632: Ok

[10:58, 15/06/2024] +60 16-880 4632: L3

[14:50, 15/06/2024] +60 16-832 2597: Inspection for 5F electrical room brick setting out (K/6)


NSC GROUP


[08:31, 15/06/2024] Azman HKL: Good morning to all πŸŒ„
Site progress photo.
15/6/2024.
21st floor. Tower A.

[08:32, 15/06/2024] Azman HKL: 3rd floor. Zone 8. Slab cast.


[08:37, 15/06/2024] Azman HKL: 7th floor. TB6. Slab formwork and rebar in progress.

[08:38, 15/06/2024] Azman HKL: 7th floor. Column rebar in progress.

[08:42, 15/06/2024] Azman HKL: 8th floor. @~WY tolong dulu. Kita sudah site walk hari itu. 3 hari sudah ya. Kita kasi settle dulu ini. πŸ™πŸ™
[08:45, 15/06/2024] Azman HKL: Hari ini ya @~WY kita ikut yang sudah agree dalam site walk..
[08:47, 15/06/2024] +60 14-379 2990: @Azman HKL minta support manpower dari maincon 4 org .. boleh ka?

[09:04, 15/06/2024] Azman HKL: πŸ‘†πŸ™8th floor. Ducting removal so plastering can proceed.
[09:05, 15/06/2024] Azman HKL: Saya satu orang boleh kah. πŸ™.

[09:10, 15/06/2024] EG Mall Shafee: @Azman HKL lvl 15 yg econmech minta buka tu rc beam…sda siap….boleh pasang ducting diorang sda
[09:27, 15/06/2024] +60 14-379 2990: Okay.. tqvm

[09:28, 15/06/2024] +60 14-379 2990: @Azman HKL @EG Mall Shafee .. kami sudah buka ducting.
[09:29, 15/06/2024] EG Mall Shafee: Terima kasih…

[09:42, 15/06/2024] Azman HKL: Ada tu Haji sana tadi tolong juga. Orang bagus. πŸ‘πŸ»

[09:50, 15/06/2024] Azman HKL: 10th floor. Electrical and ELV services at Hotel wall joint inspection in progress.

[10:27, 15/06/2024] Jimmy HKL: @~Leppong atur pasang balik ini zinc hari nie.

[10:37, 15/06/2024] +60 17-866 0355: @Jimmy HKL sudah. pasang balik

[11:33, 15/06/2024] Azman HKL: U1

[11:33, 15/06/2024] Azman HKL: U16

[11:33, 15/06/2024] Azman HKL: 21
[14:20, 15/06/2024] Azman HKL: External SESB incoming HDPE pipe connection in progress.

[14:43, 15/06/2024] +60 12-843 3877: P N10 for SESB incoming cable

[16:27, 15/06/2024] Azman HKL: External Drainage in progress.