SITE EG MALL
[10:34, 15/06/2024] +60 16-832 2597: Unscheduled site inspection for 4F electrical room for brick setting out
[10:35, 15/06/2024] +60 16-832 2597: @~Johnny we will have another inspection by 2:30pm today later for 5th floor
[10:40, 15/06/2024] +60 16-880 4632: Ok
[10:58, 15/06/2024] +60 16-880 4632: L3
NSC GROUP
[08:31, 15/06/2024] Azman HKL: Good morning to all 🌄
Site progress photo.
15/6/2024.
21st floor. Tower A.
[08:32, 15/06/2024] Azman HKL: 3rd floor. Zone 8. Slab cast.
[08:37, 15/06/2024] Azman HKL: 7th floor. TB6. Slab formwork and rebar in progress.
[08:38, 15/06/2024] Azman HKL: 7th floor. Column rebar in progress.
[08:42, 15/06/2024] Azman HKL: 8th floor. @~WY tolong dulu. Kita sudah site walk hari itu. 3 hari sudah ya. Kita kasi settle dulu ini. 🙏🙏
[08:45, 15/06/2024] Azman HKL: Hari ini ya @~WY kita ikut yang sudah agree dalam site walk..
[08:47, 15/06/2024] +60 14-379 2990: @Azman HKL minta support manpower dari maincon 4 org .. boleh ka?
[09:04, 15/06/2024] Azman HKL: 👆🙏8th floor. Ducting removal so plastering can proceed.
[09:05, 15/06/2024] Azman HKL: Saya satu orang boleh kah. 🙏.
[09:10, 15/06/2024] EG Mall Shafee: @Azman HKL lvl 15 yg econmech minta buka tu rc beam…sda siap….boleh pasang ducting diorang sda
[09:27, 15/06/2024] +60 14-379 2990: Okay.. tqvm
[09:28, 15/06/2024] +60 14-379 2990: @Azman HKL @EG Mall Shafee .. kami sudah buka ducting.
[09:29, 15/06/2024] EG Mall Shafee: Terima kasih…
[09:42, 15/06/2024] Azman HKL: Ada tu Haji sana tadi tolong juga. Orang bagus. 👍🏻
[09:50, 15/06/2024] Azman HKL: 10th floor. Electrical and ELV services at Hotel wall joint inspection in progress.
[10:27, 15/06/2024] Jimmy HKL: @~Leppong atur pasang balik ini zinc hari nie.
[10:37, 15/06/2024] +60 17-866 0355: @Jimmy HKL sudah. pasang balik
[11:33, 15/06/2024] Azman HKL: U1
[11:33, 15/06/2024] Azman HKL: U16
[14:20, 15/06/2024] Azman HKL: External SESB incoming HDPE pipe connection in progress.
[14:43, 15/06/2024] +60 12-843 3877: P N10 for SESB incoming cable