[09:45, 19/06/2024] +60 16-880 4632: L14
[09:45, 19/06/2024] Azman HKL: Request for joint inspection. 11th floor. Hotel unit. Conduit Electrical and ELV at hotel room brickwall at 10am. @~sam @Kadapi J. PROMES
[10:58, 19/06/2024] Kadapi J. PROMES: Saya cuti ni hari.
[11:22, 19/06/2024] Azman HKL: Noted.π
[16:45, 19/06/2024] Azman HKL: Thanks for inform @HIDAYA KH office Num tolong cek sekali ya itu pipe π.
NSC GROUP
[09:12, 19/06/2024] Azman HKL: Good morning.
Site progress photo.
19/6/24.
21st floor. Tower A.
[09:13, 19/06/2024] Azman HKL: 7th floor. TB6. Slab riser. Slab formwork and rebar in progress
[09:14, 19/06/2024] Azman HKL: 7th floor. TB4&TB5. Column rebar in progress
[09:15, 19/06/2024] Azman HKL: 3rd floor. Z8.
[09:22, 19/06/2024] +60 14-379 2990: Morning . @Azman HKL @~nas4rie minta tolong buka formwork riser.. ducting ready sudah
[09:41, 19/06/2024] Azman HKL: @~nas4rie minta tolong. π
[09:47, 19/06/2024] +60 12-559 6863: Gd morning @~π
πΆπ ππ½πππ Can we do a pre inspection for sesb sub station tommorrow 12:30pm? Get elec nsc to join. I will also get turnkey contractor to join. FYI, turnkey has been approved. We have 6 months to energize the sub station. Preceeded by Lunch at 1pm at our usual π
[09:47, 19/06/2024] +60 12-559 6863: @~Lawrence Yapp please send your representative ya
[12:34, 19/06/2024] +60 14-379 2990: @Azman HKL ..man, corridor level 8 kerja plastering bila boleh siap ni? Kami mau pasang balik ducting..kami takut ducting tambah damage..
[13:16, 19/06/2024] Azman HKL: @EG Mall Shafee tolong atur sama subcon GnB bro. π
[13:20, 19/06/2024] EG Mall Shafee: Ok
[13:45, 19/06/2024] Azman HKL: Tolong update ini progress work untuk meeting bsok. @~ShawnChia @Recky Econmech @HIDAYA KH office Num @~At Work
[14:05, 19/06/2024] +60 10-822 2014: Maklum
[14:07, 19/06/2024] +60 17-866 0355: Ok bo