Monday, June 17, 2024

18 JUN 2024 HKL

SITE EG MALL


NSC GROUP 

[08:43, 18/06/2024] Azman HKL: Site progress photo.
18/6/24.
21st floor. Tower A.

[08:44, 18/06/2024] Azman HKL: 7th floor. Slab rebar in progress.

[08:45, 18/06/2024] Azman HKL: 7th floor. Column rebar in progress.
[08:51, 18/06/2024] Azman HKL: Good morning all, today site coordination meeting at 2pm, please inform all respective subcons to attend including tilers, painters, aluminium NSC and all M&E. @~ShawnChia @EG MALL ECONMECH Dart @HIDAYA KH office Num @~YoonYK @~At Work

[09:36, 18/06/2024] Azman HKL: 12th floor. Hotel FFL marking at lift wall in progress. 14th to 8th floor. @~YoonYK 👆


[09:38, 18/06/2024] Azman HKL: 12th floor. ELV conduit installation at brickwall in progress.
[09:40, 18/06/2024] +60 19-821 8251: Noted thank you.

[09:46, 18/06/2024] Azman HKL: Marking di pintu ya. Macam ini.

[09:50, 18/06/2024] Azman HKL: 9th floor. Installation plumbing pipe at brickwall in progress.

[10:07, 18/06/2024] +60 18-960 2589: pungut sampah L12

[10:10, 18/06/2024] Azman HKL: 13th floor. Ceiling height inspection for ACMV services.


[11:28, 18/06/2024] Azman HKL: 14th floor

[14:33, 18/06/2024] Azman HKL: Site coordination meeting. 2pm