HIDAYAH: morning. screeding workers broke the pipe to drain the water at 13th floor room 2 @Azman HKL @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” 


HIDAYAH: dropper pipe at the 7th floor filled with sand now


[9/1/2025 11:31 AM] HIDAYA KH office Num: any workers who work there
[9/1/2025 11:32 AM] +60 12-559 6863: could be previous trades
[9/1/2025 11:39 AM] Kadapi J. PROMES: I told u😧
[9/1/2025 11:43 AM] Kadapi J. PROMES: As a MAINCON u can brief ur workers or other subcons to minimized this problems. @Edwin Chen 013 please liase with PHKL. U know better the risk of this matters. Tq
[9/1/2025 11:49 AM] Kadapi J. PROMES: There will be a lot of hacking and it may damage the structure in future if this issue unsettle. Specially Tower B. Coz mostly all pipes are concealed in r.c. slab.
[9/1/2025 12:02 PM] Edwin Chen 013: @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘”, This issue appears to have originated from your work during the screeding process, correct? To prevent future occurrences, we need to address the root cause of the problem. What are your thoughts on this approach?
[9/1/2025 12:04 PM] +60 12-559 6863: @Edwin Chen 013 I already informed here it was not caused by screeder, we will tell all other subcons including all NSCs to take care of this. If u know who damaged your pipe please report
[9/1/2025 12:05 PM] +60 12-559 6863: other NSCs won't damage the pipes while doing works in the toilets?
[9/1/2025 12:07 PM] Edwin Chen 013: Then where the sand come from?
[9/1/2025 12:07 PM] Edwin Chen 013: Please be more logical
[9/1/2025 12:07 PM] +60 12-559 6863: when the pipes are damaged, anything can flow in right?
[9/1/2025 12:07 PM] +60 12-559 6863: our screeder covered the damaged pipes using papaer
[9/1/2025 12:08 PM] +60 12-559 6863: if u persist, we go there tomorrow morning
[9/1/2025 12:09 PM] +60 12-559 6863: @Edwin Chen 013 @HIDAYA KH office Num @Kadapi J. PROMES @Azman HKL @~Johnny Chin we all meet at 13F tomorrow 9am to investigate, u can give your opinions
[9/1/2025 12:10 PM] +60 12-559 6863: u think floor screeding guys purposely damage ur pipe then cover back when do screeding?
[9/1/2025 12:10 PM] +60 12-559 6863: have some logical thinking please
[9/1/2025 12:13 PM] Edwin Chen 013: Sorry i can't attend. @HIDAYA KH office Num please attend. I am going back to KL today
[9/1/2025 12:13 PM] +60 12-559 6863: ok
[9/1/2025 12:18 PM] Kadapi J. PROMES: Sorry I can't attend also. Saya balik kampung esok. @~sam please attend.
[9/1/2025 12:34 PM] +60 16-880 4632: Can meet this afternoon 2.00pm.
[9/1/2025 12:35 PM] +60 12-559 6863: 2pm I have meeting in my HQ
[9/1/2025 2:15 PM] +60 12-559 6863: Dear all, can we have a site check later at 2.30pm? My meeting postpone to tomorrow
[9/1/2025 2:23 PM] HIDAYA KH office Num: okay boss
[9/1/2025 2:25 PM] +60 12-559 6863: We meet at 13F
[9/1/2025 2:25 PM] HIDAYA KH office Num: okay boss