Thursday, March 20, 2025

EGMALL COORDINATION(10/1/2025), EGMALL COORDINATION(13/1/2025), EGMALL COORDINATION(14/1/2025)

EGMALL COORDINATION(10/1/2025)

[10/1/2025 3:04 PM] Azman HKL: 7th floor. Zone P7.. M&E inspection for services before the cast.
[10/1/2025 4:20 PM] Azman HKL: Done inspection. @EG MALL Mr Lo @EG MALL Nasri please proceed. 👌
[10/1/2025 4:28 PM] EG MALL Mr Lo: Ok


EGMALL COORDINATION(13/1/2025)

Tower B, 10th floor. Slab inspection in progress


EGMALL COORDINATION(14/1/2025)

AZMAN: Tower B. 10th floor. M&E services inspection before slab cast.

AZMAN: Tower B. 10th floor. M&E inspection done. Please proceed. @EG MALL Nasri 👌