EG MALL NSC ( 24 MARCH 2025)
[24/3/2025 8:27 AM] Debra S. HKL: Dear Nsc, please submit your work programme. With completion date for 3 phases as per Lan’s comment
AZMAN: Morning. @~WY tolong itu paip. π
Site progress photo.
24/3/25
Tower A.
Tower A. 21st floor. Phase 1. Water ponding test. Plastering works.
Tower A. 21st floor. Slab ponding test and screeding
Tower A. 21st floor. Wall Plastering
7th floor and 7M. Plinth rebar. Water tank slab formwork in progress.
6th floor. Genset room. Equipment installation.
6th floor. Genset equipment installation.
6th floor. MSB room. Brick wall and floor screeding
Tower B.
15th floor. Slab panel.
14th floor. Wall rebar
14th floor. Slab rebar and M&E
Tower B. 15th floor.
Tower B. 14th floor.
Tower B. 14th floor.
Tower B. 8th floor. Wall skim.
[24/3/2025 10:55 AM] +60 12-559 6863: Gd evening @~π
πΆπ
ππ½πππ
. This visit rescheduled by SESB to Tuesday morning. Thanks.
[24/3/2025 10:55 AM] +60 12-559 6863: @~LO KEAM
[24/3/2025 10:57 AM] +60 19-895 9900: Apa cerita boss?
[24/3/2025 10:57 AM] +60 12-559 6863: SESB visit HV room
[24/3/2025 10:58 AM] +60 19-895 9900: Time?
[24/3/2025 10:58 AM] +60 12-559 6863: Didn’t mention
[24/3/2025 10:59 AM] +60 12-559 6863: Just said morning,
guess around 8.30am to 9am gua
+60 12-843 3889: 2th floor marking Plinth for AHU near staircase 3 ..@Azman HKL @EG MALL Nasri
[24/3/2025 1:16 PM] Azman HKL: Noted. Nanti Sy pg tgk. Yang sana 2nd floor ada 3 ka? Kita buat satu kali.