EG MALL NSC ( 22 MARCH 2025)
AZMAN: 6th floor. MSB room. @~WY sprinkler kamu.
[22/3/2025 8:26 AM] Azman HKL: @~s4yamahuk4ya88.gmail.com check lagi ya confirm itu pintu masuk muat Equipment kamu.. pasang bata supaya screeding boleh jalan.
[22/3/2025 8:27 AM] Azman HKL: @~s4yamahuk4ya88.gmail.com @HIDAYA KH office Num @~WY daily report..
AZMAN: 6th floor Genset room. Installation in progress.
Site progress photo, 
22/3/2025
Tower A.
Tower A. 21st floor. Wall plastering and screeding
7M. Slab cast
Tower B.
15th floor. Slab panel.
14th floor. Wall rebar in progress.
14th floor. Slab panel.
Tower B. 15th floor
Tower B. 14th floor
Tower B. 14th floor
Lift shaft. Bomba dan Office. Scaffolding in progress.
[22/3/2025 10:20 AM] +60 19-821 8251: we already erect up to 16th floor, so you may arrange your people to remove the platform inside which is between 16th and 17th floor. Thanks.
[22/3/2025 10:22 AM] Azman HKL: Thanks. Will arranging..
Tower B. Brick work and tai tai. Any services on brick wall please check and proceed. Before plastering. @~s4yamahuk4ya88.gmail.com @~WY @HIDAYA KH office Num .
[22/3/2025 11:32 AM] +60 12-843 3877: Di meeting kita sudah deal
Sreeding dulu
Baru kami masuk MSB PANEL
Lepas tu baru susun bata
[22/3/2025 11:48 AM] Azman HKL: Minta check pintu masuk saja bah @~s4yamahuk4ya88.gmail.com . Bukan minta masuk.
[22/3/2025 11:49 AM] Azman HKL: Screeding dulu..
[22/3/2025 12:17 PM] +60 12-559 6863: @~s4yamahuk4ya88.gmail.com kami tinggal ini wall untuk ko masuk MSB saje
[22/3/2025 12:19 PM] +60 12-843 3877: Ok Bos