Saturday, May 4, 2024

4 MAY 2024 HKL

NSC GROUP 

[08:45, 04/05/2024] Azman HKL: Site progress photo.
4/5/24.
21st floor. TA1. Slab formwork in progress. TA2. Lift wall formwork and rebar. Column rebar in progress.

[08:45, 04/05/2024] Azman HKL: 6th floor. TB5. Slab formwork, rebar and M&E in progress.

[08:45, 04/05/2024] Azman HKL: 6th floor. TB4. Slab rebar and M&E in progress. 7th floor. TB5. Slab formwork, rebar and M&E in progress. 6th floor. TB6. Slab formwork in progress.

[08:46, 04/05/2024] Azman HKL: 3rd floor. Z8. Slab formwork in progress.

[08:50, 04/05/2024] Azman HKL: Ground floor. HV room. Pipe opening rectification. @~WY

[08:50, 04/05/2024] Azman HKL: Pipe opening rectification. @~WY tolong atur. Saya maw panggil tukang cat kasi siap ni bilik.🙏🙏
[08:51, 04/05/2024] +60 14-379 2990: Okay man.

[09:10, 04/05/2024] Azman HKL: Excavation of sewer pipe at MH6 in progress.
[14:26, 04/05/2024] Azman HKL: 21st floor. TA1. Slab formwork and rebar in progress. TA2. Column and lift wall works in progress

[14:26, 04/05/2024] Azman HKL: 6th floor. TB6. Slab rebar and formwork in progress.

[14:26, 04/05/2024] Azman HKL: 6th floor. TB4. Slab rebar and M&E in progress.

[14:26, 04/05/2024] Azman HKL: 7th floor. TB5. Slab rebar and M&E in progress.
 