Saturday, April 20, 2024

21 APRIL 2024 HKL


 NSC GROUP 

[13:17, 21/04/2024] Azman HKL: Site progress.
21/4/24.
20th floor. Column rebar, lift wall, and slab support works in progress.

[13:17, 21/04/2024] Azman HKL: 5th floor. TB4.nslab formwork in progress. 7th floor. TB5. Slab support and beam formwork inprogress.

[13:17, 21/04/2024] Azman HKL: 5th floor. TB6. ST2 RC wall rebar, column rebar and formwork, 6th floor slab support works in progress





No comments:

Post a Comment

  EGMALL COORDINATION (6 18th floor. Tower B. Installation. ELV, Electrical, ACMV, FF drain pipe services done installation. 18th floor. Tow...