[08:31, 22/04/2024] Azman HKL: Monday safety ToolBox.
[09:10, 22/04/2024] Azman HKL: Site progress photo.
22/4/24.
External work. Outlet pipe to Manhole 20 in progress.
[09:10, 22/04/2024] Azman HKL: 20th floor. TA1. Column rebar in progress
[09:10, 22/04/2024] Azman HKL: 20th floor. TA2. Slab support works in progress
[09:10, 22/04/2024] Azman HKL: 6th floor. TB6. Slab support, ST2 RC wall rebar and lift wall rebar in progress.
[09:33, 22/04/2024] Azman HKL: All NSC site PIC, tolong update ya 8th floor, work progress. Any outstanding, riser room, electrical riser room please take pictures so I can bubut the Subcon. 🙏🙏.
[09:53, 22/04/2024] Azman HKL: @~zee kamu sudah start di trunking di 8th floor? Inform saya ya progress. Check itu dulu kita coordinate. Kalau masih ada masalah kita try solve di site.
[09:55, 22/04/2024] Azman HKL: Lepas saya meeting, kita pg tgk balik.
[10:31, 22/04/2024] Azman HKL: Man boleh kasi masuk dalam ka. Jangan di depan laluan.
[10:33, 22/04/2024] Azman HKL: Dalam sikit. Kalau keluar masuk bata mereka akan ambil ini ruang. Untuk loading unloading barang.
[10:33, 22/04/2024] Azman HKL: 🙏
[10:59, 22/04/2024] +60 12-843 3877: Tak dapat sudah
Lorry sangkut
[11:54, 22/04/2024] Azman HKL: Sini nanti maw pindah. Sini akan jadi entrance itu. Nanti tgk sana macam mana boleh buat dia.😩
[14:01, 22/04/2024] Azman HKL: 20th floor. TA2. Slab support works in progress.