03 AUG 23 HKL

NSC GROUP

Azman HKL: Good morning. 
Site progress picture.
3/8/2023
Ground floor. TA2. Slab cast.
Azman HKL: 5th floor slab. 5a/5b. Lift wall & column rebar in progress. 6th floor. Slab formwork & scaffolding in progress.
 Azman HKL: 5th floor, zone 4. Slab formwork in progress.
Azman HKL: 3rd floor. Zone 6. Slab formwork & scaffolding in progress.
Azman HKL: 5th floor. TB1. Slab formwork in progress.
Azman HKL: Basement, earthwork in progress.
Azman HKL: 2nd floor. TA1. Lift formwork in progress. 3rd floor slab formwork & scaffolding in progress.
Azman HKL: 1st floor. TB2. Slab formwork & scaffolding in progress.
Azman HKL: Basement 8a. Staircase formwork in progress.
Azman HKL: 5th floor. Zone 4. Slab rebar in progress.
 +60 17-866 0355: K  10
+60 17-866 0355: J 8/ k 5/ k 10/ L 11 done



















 