Azman HKL: @~YoonYK @Kadapi J. PROMES request for inspection. Lift wall and opening. 5th floor. Mall. By today 10am. 🙏
+60 19-821 8251: Noted, will do.
Azman HKL: Lift wall and button box inspection by Mitsubishi.
NSC GROUP
Edwin Chen 013: Screed the floor soon?
Raymond Chong. Y. F (HKL P. Manager): Yes
Azman HKL: Good morning.
Site progress picture.
4/8/23.
5th floor. Zone4. Slab bottom rebar in progress.
Azman HKL: 6th floor. 5a. Slab formwork in progress. 5th floor. Lift wall rebar in progress.
Azman HKL: 5th floor. 5b. Column rebar in progress.
Azman HKL: 3rd floor. Zone 6. Slab formwork in progress.
Azman HKL: Basement. Slab foundation is in progress.
Azman HKL: 5th floor. TB1. Slab rebar in progress.
Azman HKL: 2nd floor. TA1. Lift rebar in progress. 3rd floor. Slab formwork & scaffolding in progress.
Azman HKL: 1st floor. TB2. Slab formwork & scaffolding in progress. Basement, 8a. Staircase formwork in progress.