Azman HKL: Good morning.
Site progress picture.
4.06.2023. 3rd floor. Zone 5. Slab rebar in progress.
Azman HKL: 3rd floor. Zone 4. Slab formwork in progress
Azman HKL: 1st floor. Zone TA1. Slab formwork in progress.
 Azman HKL: Ground floor. Zone 7. Lift wall formwork and column rebar in progress.
Azman HKL: Basement. TB3. Column rebar in progress.
 +60 17-866 0355: basement