SITE GROUP
Azman HKL: Site progress picture.
3/06/2023.
3rd floor. Zone 5a. Slab rebar & M&E services in progress.
Azman HKL: 3rd floor. Zone 4. Slab formwork in progress.
Azman HKL: 1st floor. Zone 2. Slab & beam formwork in progress.
Azman HKL: 3rd floor. TB1. Slab formwork in progress.
Azman HKL: Ground floor. Column scaffolding in progress.
Azman HKL: Ground floor, TB2. Column rebar in progress.
Azman HKL: Conduit run at slab rebar in progress.
Azman HKL: HR riser at slab rebar.
Azman HKL: 3rd floor slab. Please check & confirm your slab opening dimension & location and get C&S& M&E consultant approval before install. TQ. Especially electrical risers and duct risers.
NSC GROUP
Azman HKL: Morning. @~DartWeirdo 🇲🇾 @~Walker Yapi maw pindah kamu punya box. Kena tu bata.
+60 16-801 0751: Ok man 🙏🏿
+60 16-801 0751: Done man
+60 14-331 3232: @Leung KH🍀 taiko morning..boleh suru org ko dtang sini grd flr dulu check ini pipe kamu masi ada guna ka..kena bata saya oh..tq
Leung KH🍀: @~DartWeirdo 🇲🇾 @~Walker Yapi
+60 16-801 0751: Nt kmi ubah bos 🙏🏿
Azman HKL: @Leung KH🍀 @Edwin Chen 013 itu pekrja jangan pakai itu kayu DOKA. Itu bukan untuk platform. Minta tukar sekarang..
Leung KH🍀: Removed 🙏🏻
Azman HKL: 3rd floor, zone 5. Conduit runs on slab in progress.
Azman HKL: Ground floor. Zone 7. Column rebar and lift formwork in progress.