06 JUNE 23 HKL

 NSC GROUP

 Azman HKL: Good morning. 
Site progress picture.
6/06/2023. Ground floor. Zone 7. Lift wall formwork & column rebar in progress.
Azman HKL: 3rd floor, zone 5. Slab rebar, formwork in progress.
Azman HKL: 3rd floor. Zone 4. Slab formwork in progress.
 Azman HKL: 1st floor. Zone TA1. Slab formwork & lift wall rebar in progress.
Azman HKL: 3rd floor. Zone TB1. Slab formwork & column rebar in progress.
Azman HKL: Ground floor. Zone TB2.
Azman HKL: Basement. TB3. Column rebar in progress.
Azman HKL: Basement, zone TB4. Slab foundation in progress.

Azman HKL: Coordination meeting. 3pm.
 Azman HKL: Casting plan. 
3rd floor. Zone 5a. 08/06/2023. Thursday.
Azman HKL: Tolong NSC jangan guna papan subcon lain. Ada subcon pg komplen ini 2 pekerja ambil papan subcon. Tolong ya.