Azman HKL: Good morning.
26/03/2023.
Zone 1&2. 1st floor slab. Formwork in progress.
Azman HKL: Zone 2D/a. 1st floor. Ramp 3 formwork in progress
Azman HKL: Zone 2D/b. 1st floor. Slab formwork & beam rebar in progress.
Azman HKL: DCC check and repair conduit at ramp2 and 1st floor slab.💪
Azman HKL: Zone 7a. Basement foundation 1st cast.
Azman HKL: Zone 2&3. Basement foundation rebar in progress.