Azman HKL: Good morning.
27/03/2023. Site progress picture.
1st floor slab and ramp2 cast.
Azman HKL: 1st floor. GL: I-L/8-11. Slab bottom rebar in progress. Target cast on this wednesday, 29/03/2023.
Azman HKL: Zone 2&3. Basement foundation bottom rebar in progress.
Azman HKL: Ramp2 casted.
Azman HKL: Zone 7a. Basement foundation cast.
NSC GROUP
Azman HKL: Ramp2 casted.
Azman HKL: Zone 7a. Basement foundation cast.
Azman HKL: 1st floor. Bottom bar in progress..
\
+60 16-801 0751: @Azman HKL evening Man. Tmorrow got meeting coordination rite?
+60 16-801 0751: We request that electrical drawing for power supply to other services panel at mall area to be bring also for discussion tomorrow ya. 🙏🏿
Azman HKL: OK Dart. NSC please take note. Tomorrow Coordination meeting 3.00pm at the site office meeting room.