Azman HKL: Good morning.
24/03/23. Site progress.
6th floor.
Azman HKL: 1st floor. GL: J-L/5-8. Slab rebar & M&E in progress.
Azman HKL: 1st floor. GL: J-L/1-5. Slab Formwork 8n progress.
Azman HKL: 1st floor. Slab formwork and rebar inprogress
Azman HKL: Zone 2&3. Basement foundation work in progress.
Azman HKL: DCC conduit in slab in progress.