Azman HKL: Site progress. 25/03/2023.
6th floor.
Azman HKL: Zone 1&2. 1st floor slab formwork in progress. Ramp2 slab rebar in progress target concrete by tommorow.
Azman HKL: 1st floor slab rebar & ramp2 rebar in progress.
Azman HKL: Zone 2D/b. 1st floor. Slab formwork and rebar in progress.
Azman HKL: Zone 2&3. Basement foundation work in progress.
Azman HKL: Zone 7a. Cleaning before casting in progress.
Azman HKL: Zone 5a. Earthwork and basement foundation work in progress.
Azman HKL: DCC on site runs conduit in ramp2 slab rebar.
Azman HKL: Econmech on site runs conduit in slab.
Azman HKL: KH on site installs pipe sleeves at slab.
Azman HKL: M&E inspection at 1st floor & ramp2 in progress.
NSC GROUP
Azman HKL: Morning. Ramp2. Bottom bar.👆
Azman HKL: TC2 is operating. Can liaise with HKL PIC & signalman if needed.
Azman HKL: KH on site installs pipe sleeves at slab.