Sunday, January 29, 2023

30 JAN 23 HKL

Azman HKL: Good morning.
Site progress. 30/01/2023
5th floor column in progress.
 Azman HKL: Basement zone 2A/a.
Azman HKL: 6th floor slab. Slab formwork in progress.
Azman HKL: Ground floor zone 1A&2A. Slab form work in progress
 Azman HKL: Ground floor. Slab & beam rebar in progress.
Azman HKL: Mall Lift pit opening.

Azman HKL: Pipe sleeve in progress.













 

Friday, January 27, 2023

28 JAN 23

 S












































28 JAN 23 HKL

Azman HKL: Good morning.
6th floor slab formwork. In progress.
Azman HKL: 5th floor column in progress
Azman HKL: Basement. Zone 2A/a. Foundation rebar in progress.
Azman HKL: Zone 2A. Ground floor slab and beam formwork in progress.
Azman HKL: Ground floor slab formwork and rebar. In progress.
Azman HKL: Zone 1D. Earthwork and pile cap rebar in progress.
Azman HKL: Morning. Im on EL today. If anything, can DM me. Sorry for any inconveniences.











 