30 JAN 23 HKL

Azman HKL: Good morning.
Site progress. 30/01/2023
5th floor column in progress.
 Azman HKL: Basement zone 2A/a.
Azman HKL: 6th floor slab. Slab formwork in progress.
Azman HKL: Ground floor zone 1A&2A. Slab form work in progress
 Azman HKL: Ground floor. Slab & beam rebar in progress.
Azman HKL: Mall Lift pit opening.

Azman HKL: Pipe sleeve in progress.













 