Azman HKL: Good morning.
6th floor slab formwork. In progress.
Azman HKL: 5th floor column in progress
Azman HKL: Basement. Zone 2A/a. Foundation rebar in progress.
Azman HKL: Zone 2A. Ground floor slab and beam formwork in progress.
Azman HKL: Ground floor slab formwork and rebar. In progress.
Azman HKL: Zone 1D. Earthwork and pile cap rebar in progress.
Azman HKL: Morning. Im on EL today. If anything, can DM me. Sorry for any inconveniences.