Thursday, October 27, 2022
Wednesday, October 26, 2022
27 OCT 22 HKL
M&E item at lift pit inspection.
Install lighting switch and socket at lift pit.
Lift pit wall dimension inspection on site with Mitsubishi.
Lift pit, wall rebar in progress..
Basement water tank area. Wall rebar inprogress.
Site progress. 27/10/2022
GL: F-I/7-11. Done concrete.
SITE group
Tuesday, October 25, 2022
26 OCT 22 HKL
Site progress: 26/10/2022. 1st floor, GL: F-I/9-11. 1st layer slab rebar.
Lift pit pile cap. Done concrete.
1st floor Column, F/7, G/7 casting plan today
Done M&E inspection.
SITE group
1st floor, GL: F-I/9-11..