Wednesday, October 26, 2022

27 OCT 22 HKL

 

M&E item at lift pit  inspection.

Install lighting switch and socket at lift pit.

Lift pit wall dimension inspection on site with Mitsubishi. 

Lift pit, wall rebar in progress..

Basement water tank area. Wall rebar inprogress.

Site progress. 27/10/2022
GL: F-I/7-11. Done concrete. 


SITE group

Lift pit wall. In progress.. @Yoon YK can you come by today. Need to double check before casting. Casting plan by tomorrow.

Done conduit installation.



27 OCT 22

 
















Tuesday, October 25, 2022

26 OCT 22 HKL

Site progress: 26/10/2022. 1st floor, GL: F-I/9-11. 1st layer slab rebar.

Lift pit pile cap. Done concrete.

1st floor Column, F/7, G/7 casting plan today


Done M&E inspection. 



SITE group


1st floor, GL: F-I/9-11..








 

26 OCT 22
















 