Wednesday, October 26, 2022

27 OCT 22 HKL

 

M&E item at lift pit  inspection.

Install lighting switch and socket at lift pit.

Lift pit wall dimension inspection on site with Mitsubishi. 

Lift pit, wall rebar in progress..

Basement water tank area. Wall rebar inprogress.

Site progress. 27/10/2022
GL: F-I/7-11. Done concrete. 


SITE group

Lift pit wall. In progress.. @Yoon YK can you come by today. Need to double check before casting. Casting plan by tomorrow.

Done conduit installation.



No comments:

Post a Comment

  EGMALL COORDINATION (6 18th floor. Tower B. Installation. ELV, Electrical, ACMV, FF drain pipe services done installation. 18th floor. Tow...