Tuesday, October 25, 2022

26 OCT 22 HKL

Site progress: 26/10/2022. 1st floor, GL: F-I/9-11. 1st layer slab rebar.

Lift pit pile cap. Done concrete.

1st floor Column, F/7, G/7 casting plan today


Done M&E inspection. 



SITE group


1st floor, GL: F-I/9-11..








 

No comments:

Post a Comment

  EGMALL COORDINATION (6 18th floor. Tower B. Installation. ELV, Electrical, ACMV, FF drain pipe services done installation. 18th floor. Tow...