Wednesday, May 3, 2023

04 MAY 23 HKL

NSC GROUP

Azman HKL: Good morning. Site progress picture. 4 May 2023. 6th floor. Column rebar.
Azman HKL: 1dt floor. TB1. Slab formwork in progress.
 Azman HKL: Basement. Zone 7A&7B rebar in progress.
 Azman HKL: Basement. lift rebar in progress. Ground floor. Slab formwork in progress. 2nd floor. Zone 4. Slab formwork.
 Azman HKL: Basement. Zone 5a. Retaining wall cast. Slab lean con.
Azman HKL: 2nd floor. Slab formwork and rebar in progress.
 Azman HKL: Mitsubishi on site check lift wall opening.
Raymond Chong. Y. F (HKL P. Manager): Any services at Zone 5A basement slab GL/11-13?
 Raymond Chong. Y. F (HKL P. Manager): The pour strip
 Raymond Chong. Y. F (HKL P. Manager): New zoning FYI














 

03 MAY 23































 

Tuesday, May 2, 2023

03 MAY 23 HKL

SITE GROUP

Azman HKL: Good morning. Site pic progress. 3/6/2023. 2nd floor & ramp3. Beam form work & rebar in progress.
 Azman HKL: Basement. Lift wall in progress.
 Azman HKL: 2nd floor. Zone 4. Slab& beam formwork in progress.
 Azman HKL: 1st floor. Slab formwork and column rebar in progress.
Azman HKL: Basement. Zone 7B&7C. Foundation rebar in progress.
Azman HKL: Basement zone 5a. Retaining wall and lift pit wall in progress.
Azman HKL: Lift pit inspection with Mitsubishi yesterday with some minor comments.
Raymond Chong. Y. F (HKL P. Manager): what are those minor comments?
Azman HKL: Basement brick work. Water tank
Azman HKL: Basement transformer area
Azman HKL: Staircase 8 area. Any conduit and opening please get RFI form for approval.


NSC GROUP


Azman HKL:Mitsubishi on site to inspect the lift button opening. Box not done. Continue tomorow.




















 

EG MALL SITE DAILY ( 31 JULY 2025)