Azman HKL: Good morning. Site pic progress. 3/6/2023. 2nd floor & ramp3. Beam form work & rebar in progress.
Azman HKL: Basement. Lift wall in progress.
Azman HKL: 2nd floor. Zone 4. Slab& beam formwork in progress.
Azman HKL: 1st floor. Slab formwork and column rebar in progress.
Azman HKL: Basement. Zone 7B&7C. Foundation rebar in progress.
Azman HKL: Basement zone 5a. Retaining wall and lift pit wall in progress.
Azman HKL: Lift pit inspection with Mitsubishi yesterday with some minor comments.
Raymond Chong. Y. F (HKL P. Manager): what are those minor comments?
Azman HKL: Basement brick work. Water tank
Azman HKL: Basement transformer area
Azman HKL: Staircase 8 area. Any conduit and opening please get RFI form for approval.