Azman HKL: Good morning. Site progress picture. 4 May 2023. 6th floor. Column rebar.
Azman HKL: 1dt floor. TB1. Slab formwork in progress.
Azman HKL: Basement. Zone 7A&7B rebar in progress.
Azman HKL: Basement. lift rebar in progress. Ground floor. Slab formwork in progress. 2nd floor. Zone 4. Slab formwork.
Azman HKL: Basement. Zone 5a. Retaining wall cast. Slab lean con.
Azman HKL: 2nd floor. Slab formwork and rebar in progress.
Azman HKL: Mitsubishi on site check lift wall opening.
Raymond Chong. Y. F (HKL P. Manager): Any services at Zone 5A basement slab GL/11-13?
Raymond Chong. Y. F (HKL P. Manager): The pour strip
Raymond Chong. Y. F (HKL P. Manager): New zoning FYI