Monday, January 9, 2023
10 JAN 23 HKL
SITE GROUP
Azman HKL: Site progress. 10/01/2023
5tg floor slab casted. Column rebar work will start.
Azman HKL: Basement. Zone 1D. Slab rebar in progress.
Azman HKL: Basement zone 2. Column rebar in progress. Wall rebar in progress. Earthwork in progress.
Azman HKL: @KH1206 @Leung KH🍀 please double check me your item here. Got FT discharge to scupper drain.
Sunday, January 8, 2023
09 JAN 23 HKL
SITE GROUP
Azman HKL: Site progress. 9/01/2023
5th floor. Rebar work and cleaning in progress.
Azman HKL: Basement. Zone 2. Earthwork and column rebar in progress
Azman HKL: Basement zone 1D. Slab rebar and earthwork in Progress.
Azman HKL: Mitsubishi on site to check lift pit dimension.
NSC GROUP
Lo. W. H (HKL-Site Engineer): Ada apa apa NSC barang sini
Lo. W. H (HKL-Site Engineer): Ni wall d basement
Azman HKL: Done M&E inspection with approval for 5th floor slab.
Azman HKL: @KH1206 @DartWeirdo 🇲🇾 @shawnstchia please double check with me and confirm this area if any services need to install before we close. GL: 1a/I-K. TQ.
KH SU YEE CHONG: we have 1 pipe in that area
Lo. W. H (HKL-Site Engineer): 🙄
Subscribe to:
Posts (Atom)







.jpeg)






.jpeg)









.jpeg)



.jpeg)




.jpeg)











.jpeg)












