Sunday, January 8, 2023

09 JAN 23 HKL

SITE GROUP

Azman HKL: Site progress. 9/01/2023
5th floor. Rebar work and cleaning in progress.
Azman HKL: Basement. Zone 2. Earthwork and column rebar in progress
Azman HKL: Basement zone 1D. Slab rebar and earthwork in Progress.
Azman HKL: Mitsubishi on site to check lift pit dimension.

NSC GROUP
Lo. W. H (HKL-Site Engineer): Ada apa apa NSC barang sini
Lo. W. H (HKL-Site Engineer): Ni wall d basement
Azman HKL: Done M&E inspection with approval for 5th floor slab.
Azman HKL: @KH1206 @DartWeirdo 🇲🇾 @shawnstchia please double check with me and confirm this area if any services need to install before we close. GL: 1a/I-K. TQ.

 KH SU YEE CHONG: we have 1 pipe in that area

Lo. W. H (HKL-Site Engineer): 🙄












 