Azman HKL: Site progress. 10/01/2023
5tg floor slab casted. Column rebar work will start.
Azman HKL: Basement. Zone 1D. Slab rebar in progress.
Azman HKL: Basement zone 2. Column rebar in progress. Wall rebar in progress. Earthwork in progress.
Azman HKL: @KH1206 @Leung KH🍀 please double check me your item here. Got FT discharge to scupper drain.