EG MALL NSC ( 12 MAY 2025)

 EG MALL NSC ( 12 MAY 2025)

Progress picture.
12/5/2025
Tower A.

Tower A. 21st floor.
Slab water proofing and testing in progress.

7th floor. ST8 and ST9. Staging for roof in progress.

Tower B.
17th floor. Slab panel and beam rebar.
16th floor. Wall rebar and panel.

Tower B.
17th floor.

Tower B.16th floor.

Tower B. 16th floor.

Tower B. 9th floor. Wall and slab panel in progress

Basement. Earthwork in progress

RAY CHONG: Econmech, please rectify this ducting level ASAP as we are closing corridor ceiling board soon, L12

L12 corridor ceiling board closing in progres
[12/5/2025 9:35 AM] Azman HKL: @~WY🫨 @EG MALL ECONMECH Dart check on site. 👏
[12/5/2025 11:25 AM] Azman HKL: @~Leppong @~WY🫨 @HIDAYA KH office Num tolong cek services di wall ya sebelum tutup. 16th floor. Tower B.
[12/5/2025 11:40 AM] +60 17-866 0355: Okman
[12/5/2025 12:32 PM] Azman HKL: NNTI Clear satu kali boss kena bata ini



[12/5/2025 12:34 PM] Azman HKL: @~Leppong nanti tolong cek sama Subcon Archi. Ini kena layout bata.
[12/5/2025 12:34 PM] Azman HKL: @~WY🫨 inform Edward pindah dia punya kotak kayu..
[12/5/2025 12:36 PM] +60 17-866 0355: O@@Azman HKL ok nanti kami cari tempat
[12/5/2025 12:36 PM] Azman HKL: Tq