EG MALL NSC ( 19 MAY 2025)
RAYCHONG : Econmech, ducting ST04
[19/5/2025 9:06 AM] +60 14-379 2990: Good morning @~π
πΆπ ππ½πππ ,
Ducting work sudah siap. Boleh proceed kerja brick wall. Tq
[19/5/2025 9:13 AM] +60 12-559 6863: Tiada naik lagi?
Grille at 6th floor
[19/5/2025 9:30 AM] +60 14-379 2990: Stop 6th floor sja.
[19/5/2025 9:30 AM] +60 12-559 6863: Dimensions? Can u provide box up?
[19/5/2025 9:41 AM] +60 12-559 6863: Consultant accepted?
[19/5/2025 10:18 AM] +60 14-379 2990: Kami tunggu final coat, then pasang grille. Baru panggil consultant..
[19/5/2025 10:22 AM] +60 12-559 6863: @~YoonYK @Azman HKL please discuss and plan power supply for lift T&C in advance, TC1 schedule to dismantle around mid June
[19/5/2025 10:22 AM] +60 19-821 8251: Noted Mr Raymond, will do. Thanks
@Azman HKL datum line 1m pls indicate on the column
We want lift the vrv outdoor. When can we lift the vrv go up?
2nd floor. Mall. Ada sudah level. @EG MALL ECONMECH Dart
[19/5/2025 11:19 AM] EG MALL ECONMECH Dart: Nt sy tarik benang level ceiling
[19/5/2025 11:29 AM] +60 12-559 6863: drawing sudah ada kah?
ECONMACH: @Azman HKL jgn buka dulu. Ksi kami psg ducting sama spk pipe sini
Bole request extend scaffolding pg atas utk buat kerja?
[19/5/2025 11:57 AM] Azman HKL: @Jimmy HKL @~fc @~π
πΆπ ππ½πππ . ECOnmech request ini scaffolding hold untuk jalan services.
[19/5/2025 12:08 PM] +60 10-809 0001: How many days they need to install their services?
[19/5/2025 12:09 PM] EG MALL ECONMECH Dart: 1 week fabricate
3-4 days install
Site progress photo.
Tower B.
19/05/2025
Tower A.
Slab works in progress
7th floor. ST8 & ST9. Roofing in progress.
Tower B.
17th floor. Slab panel and rebar
16th floor. Wall panel in progress
Tower B. 17th floor
Tower B. 17th floor.
Tower B. 17th floor
Discussion ACMV services at Mall
[19/5/2025 2:36 PM] +60 19-895 9900: Bukan DG sdh?π€
[19/5/2025 2:43 PM] Debra S. HKL: new ID
[19/5/2025 2:46 PM] +60 12-559 6863: Mall ID consultant is not DG
[19/5/2025 2:47 PM] +60 19-895 9900: Noted, Hotel & office still under DGππ»