Tuesday, May 27, 2025

EGMALL COORDINATION (24/5/2025)

    EGMALL COORDINATION (24/5/2025)

AZMAN: Tower B. 17th floor. Request for M&E services inspection. Today at 2pm. @Kadapi J. PROMES site NSC PIC, please standby on site during inspection. TQ. @~Leppong @~WY🫨 @~zee @HIDAYA KH office Num .

AZMAN: 17th floor. Tower B. Inspection in progress.

KADAPI: Ayyuuuu @Azman HKL Ini inspection kah? Everything not yet done. 
[24/5/2025 2:22 PM] Kadapi J. PROMES: Bar & Formwork not yet done lah. Please speed up so that m&e system can be install immediately. Tq
[24/5/2025 2:25 PM] Azman HKL: Iya. Noted. We push to complete by today and ready for 2nd inspection by today when all done. 👏

@EG MALL Nasri @EG MALL Mr Lo. Please take care of my PVC floor trap. This way can damage my FT. Tq
Ok noted

HIDAYAH: @Kadapi J. PROMES @Azman HKL  installation done
AZMAN: TQ.👏