EG MALL NSC ( 9 APRIL 2025)
EG MALL NSC ( 9 APRIL 2025)
7th floor. 7M..mezanine. water tank slab cast. Plinth layout check and setup.
Tower B.
15th floor. Slab cast.
15th floor. Slab panel and rebar in progress.
14th floor. Wall panel and slab