EG MALL NSC ( 11 APRIL 2025)

 EG MALL NSC ( 11 APRIL 2025)

EGMALL NASRI: For info to all subcon any material here at GF need to clear we want to start hacking for the abortive slab at 2nd floor plss take action accordingly thank you 

AZMAN: SESB, PN10, excavation work in progress



[11/4/2025 8:38 AM] Jimmy HKL: Ini area saya akan barricade dan harap bagi kerjasama untuk alihkan material kamu yg berada di kawasan ini.
[11/4/2025 8:54 AM] +60 12-559 6863: Econmech, esok bolih atur tangki kamu masuk hot water room L21, lepas tu saya mau pasang frame pintu dan siapkan bata/paitung

Site progress photo.
11/4/2025
Tower A

Tower A. 21st floor. Slab water proofing works, plastering, slab screeding.

7floor. Mezanine. Plinth formwork in progress

Tower B.
15th floor. Wall rebar
15th floor. Slab rebar and M&E

Tower B. 
15th floor. Slab panel

Incoming PN10, excavation works in progress

Request buka besi lintel beam. Diameter hot water tank 1500mm... @Azman HKL 


Minta tolong housekeeping yaa. @Azman HKL
[11/4/2025 1:51 PM] +60 12-559 6863: kasi naik dulu kita bincang esok pagi
[11/4/2025 1:51 PM] +60 14-379 2990: Okay bos..
[11/4/2025 1:53 PM] Azman HKL: @~WY🫨 Sama yang itu tadi di ground floor. Saya maw minta lain workers kasi clear. 👏
[11/4/2025 1:54 PM] +60 14-379 2990: Thank you man. 

Incoming SESB PN10 Excavation works.


No comments:

Post a Comment

EGMALL COORDINATION (26/6/2025)

   EGMALL COORDINATION (26/6/2025) [26/6/2025 4:41 PM] Azman HKL: Consultant commented. DCC ada orang maw rectify ini ASAP. 👏 [26/6/2025 4:...