EG MALL NSC ( 27 MARCH 2025)
TOWER A
Tower A. 21st floor. Slab ponding test and wall plastering.
Tower A. 21st floor.
7M. Plinth rebar and formwork. Slab rebar and M&E.
Tower B.
15th floor. Slab rebar and M&E, slab panel
14th floor. Wall rebar.
[27/3/2025 11:55 AM] +60 12-559 6863: @~YoonYK lift shaft scaffolding can proceed already
[27/3/2025 11:56 AM] +60 19-821 8251: Morning, noted will check back on site. 👌 thanks.