EG MALL NSC ( 20 MARCH 2025)
AZMAN: For info. Concrete mobile pump parking area. Standby for for casting 7M slab tomorrow. Available only on Saturday after slab casting. Please take note. @~Leppong @~LO KEAM cc. @~π
πΆπ ππ½πππ @EG MALL Mr Lo @EG MALL Nasri 
[20/3/2025 8:34 AM] EG MALL Nasri: For info yeh this area we was already backfill and compaction properly, and this area we will use its back for 7M 2nd cast beam and plinths
AZMAN: Site progress photo.
20/03/2025.
Tower A.
AZMAN: Tower A. 21st floor. Wall plastering and slab screeding preparation.
AZMAN: Tower B. 
14th to 15th floor. Slab/ wall panel and rebar
14th floor. Slab rebar and M&E.
AZMAN: Tower B. 15th floor.
AZMAN: Tower B. 14th floor.
AZMAN: Tower B. 14th floor.
[20/3/2025 3:39 PM] Jimmy HKL: MAKLUMAN
Esok bersamaan 21.03.2025 Jumaat jam 10:00 pagi bertempat dibilik mesyuarat tapak bina pihak kami Jabatan Keselamatan akan mengadakan Taklimat berkaitan OSH-Coordinator mengikut peruntukan Akta Keselamatan Dan Kesihatan Pekerjaan 1994 pindaan 2022. Kehadiran adalah wajib untuk semua subcontractor. Sekian terima kasih.