EGMALL NSC (28 NOV 2024)

  EGMALL NSC (28 NOV 2024)












[28/11/2024 1:33 PM] Azman HKL: As per morning site walk for mockup room. Tower A. 8th floor. Unit 22,21,20

1. DCC: please proceed with wiring and testing as per site discussion.

2. LSK: please proceed with the wiring and continuity test. Speaker point as per discussion on site. Request for ceiling opening at the corridor.

3. KH: seal off the pipe opening. Cover the hot water pipe and arrange for a pressure test at the corridor.

4. ECM: A. Please confirm the proposal of AC. Unit 22. B. Liaise with ceiling for FCU and return supply grill. C. Confirm the latest corridor drawing and start adjusting the duct at corridors. D. Seal off with plastering all duct and pipe opening.

[28/11/2024 1:40 PM] Azman HKL: Please be informed early by Mr Raymond:

1. Be extra careful for tiles installed.

2. Make sure extra protection, and cover the tiles while working inside.

3. No smoking in the corridors and guest room. Will be fined RM1K. Use the staircase area.

4. Any issue please highlight. We try to solve.

5. Wall plastering to soffit. All openings must seal off.