[26/11/2024 10:57 AM] +60 12-559 6863: Dear all, 8F mock up rooms ceiling frames already completed, please move in and complete all services above ceiling by this week

[26/11/2024 10:57 AM] +60 12-559 6863: Azman, please coordinate

[26/11/2024 11:24 AM] Azman HKL: Tower A. Hotel. 8th floor. Mockup room. @~LO KEAM itu construction drawing baru ikut ID sudah ada kan. Asa masalah tolong inform. @~s4yamahuk4ya88.gmail.com tolong cek on site. Atur wiring dan testing untuk mockup room. 8th floor.🙏🙏

[26/11/2024 11:27 AM] Azman HKL: @~WY atur itu AC grill untuk mockup. Testing kasi proceed. Apa outstanding inform saya. 🙏

[26/11/2024 11:27 AM] +60 12-843 3877: Noted

[26/11/2024 11:28 AM] Azman HKL: @~zee kamu juga ya.

[26/11/2024 11:29 AM] +60 14-379 2990: Okay man.

[26/11/2024 11:30 AM] Azman HKL: @HIDAYA KH office Num piping juga ya. Terutama itu mockup room. Semua lobang kalau masih ada minta tutup dulu. 🙏

[26/11/2024 11:30 AM] HIDAYA KH office Num: okay azman

[26/11/2024 11:31 AM] +60 12-559 6863: kita buat 3 bilik, room 20, 21 & 22

[26/11/2024 11:32 AM] +60 12-559 6863: semua kerja above ceiling kena plaster balik, sudah dapat warning daripada DS

[26/11/2024 11:55 AM] Azman HKL: Please be informed that today Coordination meeting postponed. 🙏