Sunday, May 26, 2024

27 MAY 2024 HKL

 SITE EG MALL



[13:40, 27/05/2024] +60 16-880 4632: @~Roxas Ng (Kai)
[13:40, 27/05/2024] +60 16-880 4632: L15
[13:43, 27/05/2024] EG Mall Shafee: Ok boss….sy inform subcon saya….
[13:48, 27/05/2024] +60 16-880 4632: πŸ‘
 

NSC GROUP




[08:42, 27/05/2024] +60 16-832 2597: Dear All, 
Kindly take note that access to ST05 from GF to 3F will be sealed off for screeding/tiling works. Please use PH up to 2F and take ST06 or ST03 for access to upper floors. Thank you for your attention. 🀝

[08:49, 27/05/2024] Azman HKL: Site progress photo. 
27/5/24.
21st floor. TA. M&E plinth works in progress.

[08:49, 27/05/2024] Azman HKL: 7th floor. TB5b. Slab cast.

[08:49, 27/05/2024] Azman HKL: 7th floor. TB6. Beam rebar works in progress.

[08:49, 27/05/2024] Azman HKL: 7th floor. Slab formwork and rebar in progress.

[08:53, 27/05/2024] Azman HKL: 2nd floor. Z8. Column rebar and ramp support in progress.

[08:59, 27/05/2024] Azman HKL: MH12 VCP pipe connecting in progress.

[08:59, 27/05/2024] Azman HKL: MH13. VCP pipe connecting in progress.
[09:07, 27/05/2024] Azman HKL: MH12 & MH13, @HIDAYA KH office Num @Edwin Chen 013 please arrange pipe connecting to MH by today ASAP. We can plan to cast the base pipe by today. πŸ™

[09:15, 27/05/2024] Azman HKL: Morning. To all, for Hotel daily report, please add Hotel unit no in your report. TQ. πŸ™

"Exp: install CW pipe for Hotel, 8th floor, unit 20,21,22. "
[09:17, 27/05/2024] Azman HKL: @~WY @King Hong Office @~s4yamahuk4ya88.gmail.com @~zee
[14:22, 27/05/2024] +60 16-832 2597: Reminder to all again; pls don’t use the ST05 from basement.. it will affect the hardening of screeding.. Tq for cooperation.

[14:40, 27/05/2024] Azman HKL: Ground floor. SPK pipe in progress.
[14:41, 27/05/2024] +60 12-559 6863: Azman, ada pipe sleeves kah?
[14:41, 27/05/2024] +60 12-559 6863: kalao tiada jangan pasang
[14:50, 27/05/2024] Azman HKL: Ini ada pipe sleeve.

[14:55, 27/05/2024] Azman HKL: 8th floor. @~WY itu trunking DCC sdah tukar. Tolong cek ya level ngam sudah ka itu. πŸ‘†
[14:58, 27/05/2024] Azman HKL: 8th floor. @EG Mall Shafee bro. Tolong atur subcon kita. Bila dia orang maw plaster itu wallπŸ‘†. Kita maw siap itu sample ducting.
[15:00, 27/05/2024] EG Mall Shafee: Td pagi sda cakap dgn joseph, saya suruh tuck dulu tu wall…then inspect…


[15:01, 27/05/2024] EG Mall Shafee: Ini ducting mcmn bro..? @Azman HKL

[15:01, 27/05/2024] Azman HKL: 8th floor. @EG Mall Shafee Ini riser sample unit, hotel no 22. Minta subcon kita orang plaster ni dalam dulu. Tolong bro. πŸ™
[15:02, 27/05/2024] EG Mall Shafee: Ok…
[15:03, 27/05/2024] Azman HKL: Ini kan pindah tolak saja. Nanti orang @~WY tolak dia.
[15:03, 27/05/2024] EG Mall Shafee: Orite bro…

[15:08, 27/05/2024] Azman HKL: Macam ini bah. Orang @~WY  sudah ejas tu duct supaya boleh plaster. Tapi dia subcon kita tidak sambung terus tu plaster. Tolong atur bro. πŸ™

[15:14, 27/05/2024] Azman HKL: 9th floor. Sprinkler pipe installation.

[15:16, 27/05/2024] Azman HKL: 9th floor. Wall hacking for thermostat conduit.

[15:29, 27/05/2024] Azman HKL: 10th floor. Mixer pipe install unit 1- 10.

[15:36, 27/05/2024] Azman HKL: 12th floor. Brickwork in progress.
[15:51, 27/05/2024] Azman HKL: 13th floor. @~WY itu duct, kalau boleh jangan kasi ikat mati dia. Sebab ini plaster wall mesti minta buka punya. @EG Mall Shafee macam mana bro ini?πŸ‘†
[15:58, 27/05/2024] Azman HKL: Reminder meeting tomorrow. Join the subcon meeting. TQ.

[16:09, 27/05/2024] Azman HKL: 17th floor. Sprinkler pipe in progress.

[16:21, 27/05/2024] Azman HKL: 21st floor. VRF plinth formwork.

[16:39, 27/05/2024] Azman HKL: 9th floor. @EG MALL ECONMECH Dart ada sudah RFI kamu? Ini 9th floor Frame ada start pasang sudah. Tolong kasi cepat RFI. Frame adjustment onsite due to HR.πŸ™
[16:43, 27/05/2024] EG MALL ECONMECH Dart: Sdh discuss sma ABLT sma RA, ah tie cakap dia mnta RA ksi instruction ksi ubah seja
[16:43, 27/05/2024] EG MALL ECONMECH Dart: nt aku tny Mr johhny
[17:04, 27/05/2024] Azman HKL: Ok. @EG Mall Shafee nanti kita follow up itu instruction dari RA.
[17:09, 27/05/2024] +60 12-559 6863: Weekly Site Coordination Meeting #1
Date: 28/05/24 Time: 2pm
Attendance:
1) GNB
2) All Archi Subcon
3) All NSCs
4) All HKL Site Staffs
Please inform all parties accordingly
@~nas4rie @Jimmy HKL @Azman HKL @Mr. Voo @~Roxas Ng (Kai) @EG Mall Shafee


No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...