Tuesday, May 14, 2024

15 MAY 2024 HKL

SITE EG MALL
 
[13:05, 15/05/2024] Azman HKL: 7th floor. TB7. Request for inspection at 2pm.. @Kadapi J. PROMES . All NSC PIC please stand by during inspection. TQ..
 

NSC GROUP

[08:24, 15/05/2024] Azman HKL: Morning. 
Site progress photo. 
15/5/2024.
21st floor. TA. Slab formwork and rebar in progress.

[08:24, 15/05/2024] Azman HKL: 6th floor. TB6. Lift wall rebar and formwork in progress. 7th floor. Slab formwork, rebar and M&E in progress.

[08:24, 15/05/2024] Azman HKL: 2nd floor. Z8. Slab cast.

[08:26, 15/05/2024] Azman HKL: External MH1 and MH2. Man hole Mould installation in progress.
[08:46, 15/05/2024] Azman HKL: Coordination meeting outcome:
 14/5/24
1. Hotel TA1. M&E services layout sample 8th floor discussed will remain as built on site. 
2. Econmech will explain to PSM about the layout sample at the 8th floor to get the approval.
3. Econmech and DCC had discussed and will adjust on site to get the corridor 2400mm ceiling height.
4. Man hole, KH will liaise with Kinnangland on adjustment of MH location on site. KH must standby on site during MH base installation so they pipe can align.
5. DCC will confirm if any changes of location of the MDF room or JC9C on site. Layout of the PN10 pipe
6. DCC to check if that MSB door opening is enough space for their equipment and.
7. MSB plinth at MSB room, 15th floor.
8. 21st floor Plinth/slab opening confirmation and layout KH and Econmech.
9. All the obstruction issues on site update especially  riser room.
10. Mitsubishi Lift shaft clearing, lift motor room and lift shaft verticality issues.
11. The ID drawing issues.
[08:48, 15/05/2024] Azman HKL: @~ShawnChia @~WY @+60 10-822 2014 @Recky Econmech @~YoonYK @HIDAYA KH office Num please remind me if any thing I miss.
[08:55, 15/05/2024] Azman HKL: Submit % of work progress by today. TQ.🙏
[13:18, 15/05/2024] +60 12-559 6863: Dear King Hong, Cold Water Tank Pump Room required roof and brick wall? Or just bare?
[14:50, 15/05/2024] Edwin Chen 013: There is roof in the area.
[14:50, 15/05/2024] +60 12-559 6863: thanks


[15:19, 15/05/2024] EG MALL Mr Lo: @HIDAYA KH office Num  tolong sambung tu pipe pergi manhole berkenaan ...supaya boleh bakfill
[15:20, 15/05/2024] HIDAYA KH office Num: okay mr lo
 