[08:53, 14/12/2023] Azman HKL: Good morning. 
Site progress photo.
14/12/2023
Basement. Z5c. Slab rebar, plinth rebar in progress.

[08:53, 14/12/2023] Azman HKL: Basement. Z9. Lift pit wall rebar in progress.

[08:53, 14/12/2023] Azman HKL: 8th floor. TA/2. Lift wall rebar in progress

[08:53, 14/12/2023] Azman HKL: 5th floor. TB5. Slab rebar in progress.

[08:53, 14/12/2023] Azman HKL: 9th floor. TA/1. Slab formwork in progress. 8th floor TA/2. Column rebar in progress.

[09:35, 14/12/2023] Azman HKL: DCC genset acoustic item delivering to ground floor temporary storage.

[09:57, 14/12/2023] Azman HKL: @HIDAYA KH office Num tolong jumpa/call supervisor Joseph dulu tgk itu tempat dia maw jalan bata dia cakap. 🙏🙏
[10:02, 14/12/2023] HIDAYA KH office Num: kami tengah kasi pindah sekarang


[13:21, 14/12/2023] HIDAYA KH office Num: @Azman HKL we request for surveyor to do marking at 9th floor TA1 as soon as formwork done.
[13:30, 14/12/2023] Edwin Chen 013: Ensure precision in the initial attempt in order to avoid any delay


[14:00, 14/12/2023] Azman HKL: @Edwin Chen 013 @HIDAYA KH office Num cuba cek sana. Macam sda marking. Double cek saja ya. Ada sda tu.
[14:02, 14/12/2023] Azman HKL: Sama2 cek supaya lebih kofindem..
[14:03, 14/12/2023] HIDAYA KH office Num: okay
[14:03, 14/12/2023] Edwin Chen 013: I mean the marking by your surveyor




[14:27, 14/12/2023] HIDAYA KH office Num: site still not ready for installation
[14:35, 14/12/2023] Azman HKL: @~.Fazli ini TB5, 5th floor kan..

[15:55, 14/12/2023] Azman HKL: Genset & Transformer lifting discussion with HKL, DCC, Safety and Supplier. As per discuss. 1. Genset and Transformer will be lifting altogether by the supplier. 2. Equipment will be lifted to the 6th floor and pushed to a temporary storage until the exact room area is ready. 3. Equipment will be covered by canvas and plywood by the supplier, HKL will provide temporary roofing 4. Before equipment arrival, HKL requested the lorry crane driver to come again and check the road & area condition for lifting. (Please comment if there is any missing or to add).

[16:23, 14/12/2023] Azman HKL: New Casting Plan
BF - 9B RC wall - 14/12/23
BF - 9C -15/12/23
BF - 5C/a - 15/12/23
9F - TA/1 - 16/12/23👈
6F - TB5 - 16/12/23
6F - Z6 - 19/12/23
9F - TA/2 -21/12/23
6F - TB3 - 21/12/23
4F - Z7 - 21/12/23
6F - Z4 - 26/12/23
Please coordinate material, man power and drawing onsite. Date may be changed due to site condition.
[16:29, 14/12/2023] Azman HKL: Noted. Will push them so M&E can start installing.
[16:29, 14/12/2023] Azman HKL: Ground floor. Temporary storage on the ground floor for genset acoustic equipment