Thursday, April 25, 2024

26 APRIL 2024 HKL

 NSC GROUP


[08:28, 26/04/2024] Azman HKL: Site progress photo.
26/4/24
20th floor. TA2. Slab rebar and M&E in progress

[08:28, 26/04/2024] Azman HKL: 20th floor. TA1. Column rebar and formwork.

[08:28, 26/04/2024] Azman HKL: 6th floor. Slab supports shoring in progress. Lift wall rebar in progress

[08:28, 26/04/2024] Azman HKL: 7th floor. TB5. Slab formwork in progress.

[08:28, 26/04/2024] Azman HKL: 6th floor. TB4. Slab formwork in progress.

[08:50, 26/04/2024] EG MALL Mr Lo: @HIDAYA KH office Num

[10:15, 26/04/2024] Azman HKL: 3rd floor. @~WY tolong atur cepat tutup ini. Kalau boleh buat ini hari. Painting sudah jalan sini. 🙏🙏

[10:17, 26/04/2024] Azman HKL: Ini juga ya. Cek semua pipe la ya di M&E room wall. @~WY

[10:31, 26/04/2024] Azman HKL: 3rd floor. Scupper drain @EG MALL Mr Lo @HIDAYA KH office Num kita buka sajala semua pipe scupper drain ni.🙏

[13:24, 26/04/2024] Azman HKL: 20th floor. TA2. Slab rebar, formwork and M&E in progress.

[13:24, 26/04/2024] Azman HKL: 20th floor. TA1.column rebar in progress.

[13:29, 26/04/2024] Azman HKL: 6th floor. TB4. Slab formwork in progress. 7th floor. TB5. Slab formwork in progress.

[13:53, 26/04/2024] HIDAYA KH office Num: 3rd floor - 2nd water tank

[14:43, 26/04/2024] Azman HKL: 10th floor. TA1. Brickwall in progress.

[14:56, 26/04/2024] Azman HKL: Iya ok. Tunggu siap dulu ini. 🙏🙏 Mereka sedang bubut di bawah ni pasang formwork.

[15:11, 26/04/2024] Azman HKL: Ni di st06 2F , @Azman HKL  bulih pas kah ?
[15:12, 26/04/2024] Azman HKL: @~Rimon Joseph @~WY Ini kasi repair baik dia. Tokong cek ya. 2nd floor. ST6.
[15:14, 26/04/2024] +60 18-960 2589: @Azman HKL bukan pipe kami
[15:14, 26/04/2024] Azman HKL: Iya ok. 🙏🙏
[15:17, 26/04/2024] +60 19-809 6068: Noted, nanti kami repair 🙏🏻
[15:18, 26/04/2024] Mr. Voo: Tolong check jg pg atas dan lain .. thxs
[15:22, 26/04/2024] +60 19-809 6068: Okay bos. 🙏🏻

[16:09, 26/04/2024] Azman HKL: 20th floor. Pre inspection in progress.
[16:32, 26/04/2024] EG MALL Mr Lo: @Edwin Chen 013 the scupper drain at 21st floor tower A
[16:32, 26/04/2024] EG MALL Mr Lo: please see where your discharge point should be
[16:32, 26/04/2024] EG MALL Mr Lo: thanks
[16:35, 26/04/2024] +60 16-832 2597: Dear All NSC have works at GF HV rooms, we have locked and secured the doors.. Pls look for @Azman HKL for the keys to unlocked it. TQ