[14:17, 26/04/2024] Azman HKL: 20th floor. Tower A. Request for M&E inspection at 3.00pm. @Kadapi J. PROMES . NSC site PIC please stand by at site during inspection. @~s4yamahuk4ya88.gmail.com @~WY @HIDAYA KH office Num @~zee
[14:26, 26/04/2024] Kadapi J. PROMES: π
[16:22, 26/04/2024] Kadapi J. PROMES: Banyak lagi belum siap formwork dan rebar boss ku @Azman HKL
[16:22, 26/04/2024] +60 16-837 8881: Confirm ni malam mahu cast ?
[16:27, 26/04/2024] Azman HKL: Confirm ini malam.
[16:28, 26/04/2024] Azman HKL: Iya bos. Sekarang kami push subcon kejar ini tempat. Sekrang tambah org sudah di atas sini.
[17:21, 26/04/2024] Azman HKL: Plumbing inspection done. M&E services inspection will continue after all services work are installed. @~s4yamahuk4ya88.gmail.com @~Leppong @~zee @~WY @~Rimon Joseph
NSC GROUP
[08:28, 26/04/2024] Azman HKL: Site progress photo.
26/4/24
20th floor. TA2. Slab rebar and M&E in progress
[08:28, 26/04/2024] Azman HKL: 20th floor. TA1. Column rebar and formwork.
[08:28, 26/04/2024] Azman HKL: 6th floor. Slab supports shoring in progress. Lift wall rebar in progress
[08:28, 26/04/2024] Azman HKL: 7th floor. TB5. Slab formwork in progress.
[08:28, 26/04/2024] Azman HKL: 6th floor. TB4. Slab formwork in progress.
[08:50, 26/04/2024] EG MALL Mr Lo: @HIDAYA KH office Num
[10:15, 26/04/2024] Azman HKL: 3rd floor. @~WY tolong atur cepat tutup ini. Kalau boleh buat ini hari. Painting sudah jalan sini. ππ
[10:17, 26/04/2024] Azman HKL: Ini juga ya. Cek semua pipe la ya di M&E room wall. @~WY
[10:31, 26/04/2024] Azman HKL: 3rd floor. Scupper drain @EG MALL Mr Lo @HIDAYA KH office Num kita buka sajala semua pipe scupper drain ni.π
[13:24, 26/04/2024] Azman HKL: 20th floor. TA2. Slab rebar, formwork and M&E in progress.
[13:24, 26/04/2024] Azman HKL: 20th floor. TA1.column rebar in progress.
[13:29, 26/04/2024] Azman HKL: 6th floor. TB4. Slab formwork in progress. 7th floor. TB5. Slab formwork in progress.
[13:53, 26/04/2024] HIDAYA KH office Num: 3rd floor - 2nd water tank
[14:43, 26/04/2024] Azman HKL: 10th floor. TA1. Brickwall in progress.
[14:56, 26/04/2024] Azman HKL: Iya ok. Tunggu siap dulu ini. ππ Mereka sedang bubut di bawah ni pasang formwork.
[16:09, 26/04/2024] Azman HKL: 20th floor. Pre inspection in progress
[15:11, 26/04/2024] Azman HKL: Ni di st06 2F , @Azman HKL bulih pas kah ?
[15:12, 26/04/2024] Azman HKL: @~Rimon Joseph @~WY Ini kasi repair baik dia. Tokong cek ya. 2nd floor. ST6.
[15:14, 26/04/2024] +60 18-960 2589: @Azman HKL bukan pipe kami
[15:14, 26/04/2024] Azman HKL: Iya ok. ππ
[15:17, 26/04/2024] +60 19-809 6068: Noted, nanti kami repair ππ»
[15:18, 26/04/2024] Mr. Voo: Tolong check jg pg atas dan lain .. thxs
[15:22, 26/04/2024] +60 19-809 6068: Okay bos. ππ»